Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

How to add an existing issue to a Portfolio plan?

Using Jira 7, self-hosted. Portfolio 3.5

I created a plan, added a few issues, and everything is great. But then I noticed that I forgot to add one issue to the scope and I cannot find any way to add more, other than the "Create issue" button.
To be clear, I do not want to create a new issue, I want to add an already existing issue to my plan.

1 answer

1 accepted

1 vote
Answer accepted
Cristiano Mariano
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Jul 03, 2019

If you go to Issue Sources and click Edit, you will have the same options you had when you created the plan.

Thank you, Cristiano. That did it, I was hoping there was a simpler way, but this solution worked.