How is overload calculated?

Louise Nielsen August 30, 2019

Hi,

How is overload calculated?

Capture5.PNG

Is it the teams capacity in the 23 extra days? 

 

Regards

Louise

1 answer

0 votes
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 12, 2019

Hello Louise,

That view in question from your screenshot, is the Release report. The release is scheduled to end in another 23 days because the work assigned to a release is larger than the available team capacity, and this makes the release turn red.

In this release report view, the capacity is calculated using the team's velocity and the scheduled work for the release. For example, the team can finish a maximum of 30 story points in each sprint, the capacity will be overloaded if the work assigned to a release that has a fixed end date sometime in the next sprint are estimated more than 30 story points.

Some additional details on the settings can be seen in:

Regards,
Earl

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events