The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do i create a program Initiative that spans multiple plans?

Russell Bailey
Contributor
September 6, 2018

I created a Program that contains several plans.  I would like to create an Initiative at the Program level that is the Parent of Epics at the Plan level.  Is there a way to do that?

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Jack Harding
September 12, 2018

Hey @Russell Bailey!

You can define an initiative that spans several plans by ensuring that the initiative is defined by the issue sources of each plan. 

By definition, however, each plan is independent of the others, so the initiative would show up on the schedule view for each of the plans it is defined in.

Furthermore, as each plan is independent and defined/calculated by the issues in each plan, the estimate and progress "roll-up" of the initiative across each plan will be defined only by the issues in that plan. 

-Jack

Russell Bailey
Contributor
September 12, 2018

Thanks Jack.  I'll give it a try.

Jack Harding
September 12, 2018

Absolutely @Russell Bailey! Let me know if you have any other questions :)