Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

How do I set Later release to start relative to previous release date?

Based on knowledge base articles, the Later release is supposed to start after the last created release date.  However, mine is set to start "as early as possible" which is scheduling work concurrently with work prioritized into name releases.

ASK | How can I change this setting so it doesn't start until named releases end?

1 answer

same issue, nearly two years later.  disappointing you got no guidance or response.