Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

How do I get "start and end date" of an Epic to self populate based on its story dates?

Hi just started a trial of Advanced Roadmaps, I'm trying to use an Epic as an overall project, inside the story's will be the main 'packs' of information, each pack is built up of the sub tasks.

I want the stories to dictate how long the overall project takes. and remain dynamic, so if I change an end date of one of the stories, the overall end date of the Epic changes. is this possible or am I using this for the wrong reasons?

1 answer

1 accepted

0 votes
Answer accepted

Ah I've found it sorry! - it's in view settings "Show a roll-up of dates in the fields and timeline sections."