Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

How do I get Jira Portfolio to respect existing sprints?

When I try to create a plan in Jira Portfolio, Portfolio seems to pay no attention at all to the existing (and past) sprints for my project(s). It assigns issues that are already in an active sprint to sprints in the plan, and does not respect the calendar dates of the existing sprint in my project. 

How do I

  1. get future sprints in Portfolio to start at the end of the current one for my project in Jira, 
  2. keep the items in the current sprint there and not put them in future sprints, and (if possible), 
  3. show past sprints?

1 answer

0 votes
Belto
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Mar 25, 2019

The Scope view does not take into account closed Sprints.

To have more control over the future, past and current Sprints, you will have to use the Scope filters to define over what period of time the Plan should look at.

See Using scope filters for more details.