I must be missing something obvious but I can't see how to add existing Jira Epics to an already created Plan.   (When I created the Plan I was getting server timeouts. The only way around that was to created the plan without any Epics.).  I am running Portfolio 2

2 answers

1 accepted

4 votes
Answer accepted
Joel Feldman
Contributor
October 24, 2017

Nevermind.  I found that wizard through:

  1. <plan> ...  Configure
  2. Issues sources
  3. Edit sources
Ludovic Allouch
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 15, 2021

4 years later, this auto-answer saved me from a bad week-end ;)

Like Kristen Brown likes this
0 votes
Grant Willison
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 20, 2024

the accepted answer doesn't work. Neither do jira plans