If I open up a plan and just hit calculate (without prior changing any target dates or fields) it completely screws up my calculation based on today as start date. How do I revert this?
Hi Christian,
There is currently an open Suggestion to have a feature implemented in Portfolio to undo changes made by hitting calculate. Please vote on JPOSERVER-1761 - Provide a feature to rollback/revert changes after user click Calculate and add your use case to the comments for impact.
As a suggestion to help mitigate this in the future please take a look at the Community post When using "Calculate" in Portfolio, all my releases are badly assigned. What can I do? It suggests using multi-scenarios to experiment with the plan - "the calculation will only apply to the current scenario you are working with."
Cheers,
Branden