How can I postpone the start date of my plan in Portfolio?

Meggie Bouchard
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 25, 2018

So, I'm planning ahead for the next quarter. Basically, the plan in portfolio needs to start next week, July 2nd.
problem is that we've been customizing Portfolio since one month now, so the start date was one month ago. Until the end of June, we are not using Portfolio to plan, but simply jira. 
How can the future work to get done at a later defined date?

1 answer

0 votes
Wessel Donkervoort June 26, 2018

You can use "Earliest Start Date" for this. It's a field that, unfortunately, can only be configured in Portfolio for Jira itself.

Meggie Bouchard
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 26, 2018

Yep. That's what I did. For some reason it didn't recalculate properly at first, but then the more I was committing changes, at some point it just got updated with the correct start date. It's a little bit of a struggle to have to put the earliest date for all single epics. Just a simple plan start date would be better, but it worked. Thanks! 