Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

How can I postpone the start date of my plan in Portfolio?

So, I'm planning ahead for the next quarter. Basically, the plan in portfolio needs to start next week, July 2nd.
problem is that we've been customizing Portfolio since one month now, so the start date was one month ago. Until the end of June, we are not using Portfolio to plan, but simply jira. 
How can the future work to get done at a later defined date?

1 answer

You can use "Earliest Start Date" for this. It's a field that, unfortunately, can only be configured in Portfolio for Jira itself.

Yep. That's what I did. For some reason it didn't recalculate properly at first, but then the more I was committing changes, at some point it just got updated with the correct start date. It's a little bit of a struggle to have to put the earliest date for all single epics. Just a simple plan start date would be better, but it worked. Thanks! 