Having issues with exporting dependencies created in portfolio using the new planning interface.

Rosemarie Oelrich
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 22, 2020

Unable to export dependencies created in portfolio to .csv file created from a plan. Incoming and Outgoing dependency columns are not being exported.

1 answer

0 votes
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 7, 2020

Hello @Rosemarie Oelrich ,

Thank you for pointing this one out, and it looks like a Bug in the new Export the plan feature recently released in 3.23 and later versions of portfolio.

I created the following Bug Report to track this, please add yourself as a watcher if you would like to receive updates on the status of the fix:

Regards,
Earl