Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Does anyone know how Planned capacity is calculated in Portfolio for Jira?

I have setup a project in Portfolio for Jira. When I look at Reports - Sprints and take a look at Planned capacity Sprint, the amounts do not equal to the actual number of Story points in that sprint. This leads me to believe the number is being calculated elsewhere.

 

But how?? I read the documentation and it was of no help. Does anyone know how Jira calculates the Planned Capacity?

1 answer

0 votes
Gabriele Franck
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Feb 13, 2019 • edited

Hi, Nitin

Is your plan overbooked in Portfolio? Could you please provide me a screenshot of your capacity view?

 

Gabi

Default Velocity is 47 with 7 people working 40 hour week.capacity.jpg

The first Sprint itself has only 61 Story Points