Hi, I find the Dependencies report very useful to quickly show dependencies between teams. However now the view is starting to get blurred by dependencies that are already closed, in closed sprints. How can adjust what issues to show? I'd like to show only dependencies in all active and all future sprints for example. Not closed sprints. I've been looking around a lot for this.
Hi @Tommy Bergquist
Welcome to the community
You will need to alter how long "done" issues show in the plan for (see below)....or create a copy plan that doesn't show them at all. As what shows on the report is what is filtered into the plan via the Issue Sources.
Go to the Configuration of the plan and adjust "exclude any completed issues after" to as low as you desire.
Can't believe I missed that. Thanks alot, Curt!