Cross Project Releases

James Strangeway
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 17, 2017

I am new to using Portfolio and I am wondering if when you have finished all of the project level releases of a CPR is the CPR supposed to auto fall off in or what is the expected workflow for the no longer needed CPR at the Portfolio level?  It is a little noisy if it stays.  Thanks.

1 answer

0 votes
Clare
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 14, 2017

Hi James,

The expected workflow in this case would be to delete the CPR once it is completed. At the moment there is no other workaround for this.

There is a feature suggestion for this issue here https://jira.atlassian.com/browse/JPOSERVER-1918 which you can vote on.

Thanks,

Portfolio Server Team