Hi,
is there an easy way in portfolio to check for a specific plan if one or more of the scheduled end dates is later than the related target end date?
If not I think this would be a nice feature for easier planing and also to check current plans vs targets.
Hello,
Switch the Scope View to Target Schedule under the schedule settings as Described here, and you will get a graphical overlay on the timeline showing a dark blue Bar as the Target date range vs the Scheduled Date range and if the items are overlapping as desired or not.
-Earl
Hi,
thank you for the answer. I've already seen this view. However I'm searching for a mechanism which is more "eye-catching". For example something like the timeline which becomes red when a release is overbooked. Or a list which show all critical target dates.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.