Hoping I can get some help resolving an issue I am having with capacity in portfolio. We have specialists working on projects that can be up to 6 months long. When I create an issue, epic, and feature, I have been inputting all the correct information - estimated time, start date, end date etc. On all levels. I also assign the issue to a sprint.
The problem is that in portfolio, the estimated time does not roll over and spread across future sprints. Which means all of our specialists appear over capacity. Please see image attached, our staff members are working 128 days in 10 day sprints.
Our staff members can be working on up to 3 projects at once, and we have 50 staff members in our faculty. So the resolution to this problem cannot be that we have to create an issue every 10 days for each project.
Is there anyway way for the hours to spread over multiple sprints? Or to resolve this problem?