I have a plan I am building that tracks deliverables across two teams, one tracks in points, and other in hours.
This doesn't seem to work. Is there a setup step I need to take?
Ken
Hi Ken!
Are you using two different sources for your plan? You do have the option to convert story points to days on the issue sources you choose for Portfolio, so you may be able to select one source to use points and the other to use days.
I have one dev project that estimates in points and another project in marketing that only estimates in hours but I need to include them in one plan so that I can make sure they are both aligned for a product release.
So engineering is run via Scrum using Points
Marketing is run via Kanban using hours.
I have them both in one Portfolio plan and want to use the Calculation tools without having to convert marketing hours by hand.
Can I do that?