Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Can we use skills without stages?

Hi, 

In our portfolio plan we configured several skills ( like team lead, developer, architect etc. ), but do we need to configure stages as well for using it properly, or can we use skills without stages? 

Thank you!

1 answer

0 votes
JamieGeorgeson
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Apr 27, 2018

Hi Jeroen,

Yes - you are able to use Skills without Stages.

You can break down an estimation for an issue by skill (e.g. 25% architect, 75% development). You can assign Skills to Team Members in a Plan, and Portfolio will schedule issues according to the availability of skills in the team. This can by useful for finding bottlenecks in planning introduced by work items requiring specialised experience.

Stages are more about capturing sequential activities within a work item (e.g. a design stage followed by implementation).