The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Can i exclude a specific issue type from Portfolio plan?

Katerina Stasik
Contributor
October 23, 2018

I want a certain issue type, e.g. TASK to never be included in my portfolio planning (while still using it in the project). Is it possible to do do? 

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Syauqi
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 25, 2018

Hi Katerina, 

You may want to re-configure the issue source to a filter instead:

project = <Current Project> and issuetype not in (Task)

Here's the step to change plan's issue source:

  1. Go to your plan > click Screen+Shot+2016-02-01+at+9.07.08+am.png located next to the plan name > Configure > Issues sources.

  2. Click Edit Source.

  3. Connect to existing filters and click Next.

     

  4. Select the relevant releases and confirm what's in scope, then click Next.

  5. Confirm the issues that will be in the scope and select Done.

Note:

Changing issue sources will affect your plan's scope, releases, and teams.

Feel free to See Configuring your plan issue sources.

Let me know if this is what you are looking for, otherwise, please do elaborate so that we could better understand the issue.

Cheers, Syauqi