Hello all,
I have a question regarding the auto-schedule criteria. I have a Sprint of 2 weeks time and team velocity of 55 story point/ Sprint.
In this plan, there is only 1 story with highest priority, however, in the auto-schedule result, it is not planned in the first Sprint.
I have also try the ranking, but seems it is not related either.
Does anyone know the logic of it? Thanks. uto-schedule? Thanks.
If you change the hierarchy filter to just show stories - what does the ranking look like?
Stories and epics are ranked independently (every issue in Jira has a global unique rank) and a story can be ranked higher than another story belonging to the a high ranked epic.
The priority field is not considered by the auto-scheduling algorithm, but the rank is.
Regards,
Dave
Check if there is a dependency on story or it is assigned to a release in future.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.