We think about using Advanced Roadmaps for high level planning on initiative level. Every initative has a successor (set by a dependency), estimated hours and an assigned team. Automated planning is working fine, initially. But when an initiative is delayed our must be set to another start-date as set by the automatic-planner, the subsequent initiatives are not moved as well. They stay on the same start- and end-date, even if I use the automatic-planner. Any hints or tips to handle "usual" delays or plan adaptations, by not manually moving all dependent tasks? Thanks in advance