Advanced roadmaps - Show warning to linked dependency at initiative level

Yuri Suppa January 15, 2024

Hello,

we have set up the initiative level on top of the issue type hierarchy and testing the child epic/story/task warnings with target dates exceeding the parent end date, which works fine. However I can`t seem to find how to show a warning in another initiative that I`ve linked as a dependency:

example: IN-1 is linked to IN-2 with a "is blocked by" link type. IN-1 has a child epic EP-1 which has a child story ST-1 with an end date set later that EP-1, therefore I see a warning on IN-1, EP-1 and ST-1 but no warnings on IN-2. Is there a way to enable this?

1 answer

0 votes
Crystelle S
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 29, 2024

Your warning would show in the dependency field as opposed to the warning you see for dates of children to the left.