Hi floks!
It seems I have a problem with Advanced Roadmap.
I have this Plan configured with two boards, SS and SIX. Each one come from a different Jira Project.
There are 3 problems:
1) As you can see, the current sprint appears cutted, and as much as I struggle about it, I can't figure out why.
2) The sprints SP allocated don't fit with backlog sprint estimates: Look the examples of OCT 1/2 and OCT 2/2
3) Dates also don't fit: Look again OCT 1/2 and OCT 2/2.
Does anybody any idea about what's is going on here?? I'm going crazy :S
Thanks in advance
Hi Marcelo,
Can you open Oct 1/2 sprint flyout (move the mouse on the sprint bar in the Advanced Roadmaps timeline to show the flyout) and share the screenshot of the sprint properties here.
Also, I would recommend that you raise a support request (via https://support.atlassian.com/contact/ ). Creating a support request will yield a faster response as a Support Engineer will be better placed to assist you here.
Regards,
Sara
Hi Sara,
Thanks for your answer. I've just opened a ticket to Atlassian.
This is the flyout.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey Marcelo,
The screenshot doesn't show the sprint properties. But don't worry, it's better to not share your plan info here, you might want to remove the screenshot ;)
Thanks for creating the support ticket, I am sure our support team can assist you with the issue.
Regards,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
It is hard to tell without having access to your projects and backlogs, but I've seen something like this before and the answer was; due to the Exclude any completed issues after = XX days (in the Exclusion rules section of the plans configuration) the completed work wasn't considered part of the plan, thus the discrepancy.
In that case they had a very small completed window (only 3 days), changing it back to 30 days resolved the issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Curt, and thanks for your reply.
I followed your advices and setup it in 30 days
It changed from 355 to 461 issues, but now the problem is still pretty similar. The view looks like that
The problem seems in SS-3381 goal issue. I've added it to the right team and no sprint, but nothing.
:S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I notice in your Exclusions there are some issue types being excluded, that could be part of the problem as well. Try removing them from the exclusion list and see what happens
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Curt. I didn't but still nothing. Finally I've followed the Sara advices and I've opened a support ticket. Thanks for your help!!