Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Advanced Roadmap capacity planning with a Kanban Board

Hello,

How can I mange capacity planning in Kanban Boards with Advanced Roadmaps?

What is the Jira issue field that would gather estimate to influence the capacity on the timeline ?

 

With Scrum it's clear, but on Kanban when using time tracking Jira field to collect time log, I can not see any impact on the time line from a Kanban board issue source.

 

1 answer

0 votes
Craig Nodwell
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 02, 2022

Hi @AS please refer to this article.

Hi @Craig Nodwell ,

Thanks for the link.

"For Kanban teams, work is broken down into iterations which each last one week. You can set the weekly capacity of a Kanban team in either days or hours, but the length of the iteration cannot be changed"

Above is the only paragraph referring to Kanban capacity planning with Advanced Roadmaps from the article.

 

Does it mean that there is no estimation to allocate to issues?

From the simulation perspective, it is not obvious to picture on time line iterations plan views how data from Jira issues affect capacity.

1- How to estimate on Kanban tickets? Where do you allocate estimation values from tickets? Is it from the time tracking field?

2- How does this estimation from Jira tickets appear on time line Plan view of Advanced Roadmap? For example when the estimation 0f work is above capacity.

Best regards

Craig Nodwell
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 02, 2022

Please have a look over this post.  

Hi @Craig Nodwell ,

I have found what I have been looking for.

The field "Estimate" Advanced Roadmap corresponds to the section Remaining estimate in Jira ticket.

 

Thanks