i have issues that estimated for 2 days and the scheduled in portfolio (start -end date )display the issue only as 1 day
thanks!
Hi Natalie,
Go to the "plan configurations >> Scheduling >> Maximum assignees per story", the default value here is going to be 3, so even though you have 16 hours for an 8 hour work day up to 3 team members can be assigned to the issue to spread the load of that issue across the associated team members.
You can either reduce the "Maximum assignees per story" value to 1 so that there is only one assignee per story, and you should be all set.
Additional details on the steps for configuring this setting can be seen here:
Regards,
Earl
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.