Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Deleted user
0 / 0 points
Next:
badges earned

Your Points Tracker
Challenges
Leaderboard
  • Global
  • Feed

Badge for your thoughts?

You're enrolled in our new beta rewards program. Join our group to get the inside scoop and share your feedback.

Join group
Recognition
Give the gift of kudos
You have 0 kudos available to give
Who do you want to recognize?
Why do you want to recognize them?
Kudos
Great job appreciating your peers!
Check back soon to give more kudos.

Past Kudos Given
No kudos given
You haven't given any kudos yet. Share the love above and you'll see it here.

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Wrong tasks sorting in auto scheduling

I need sort all tasks by my priority. Its required for me. Plz watch screenshot.Portfolio_sorting.jpg
Is it possible?

2 answers

I have the exact same problem.  I am completely unable to control the schedule that Portfolio generates, and therefore JIRA Portfolio is essentially useless.  (For the Atlassians, that's issue JST-213949 in your system.)

I asked about it here and my question has apparently been deleted.  Then I asked support and they advised me to sort my tasks by priority.  I repeated that I had done that from the start and it had no effect on the schedule.  And that was the end of it.  JIRA Portfolio remains useless to us.  We eliminated all of the factors listed on the Portfolio support page that might affect the scheduling:

https://confluence.atlassian.com/jiraportfoliocloud/recalculating-the-schedule-715263582.html

Maybe one of those things is affecting your scheduling?

In our case, we tried sorting the tasks, epics AND initiatives to try to influence the schedule and it had no effect.  Rearranging the ranking will cause the schedule to recalculate, and things will move around.  But we have been unable to make it schedule the next priority as the next task on the schedule.  So we still schedule sprints manually and we'll probably discontinue JIRA Portfolio since it doesn't work.

Ah, here was my original question about this:

https://answers.atlassian.com/questions/39579938/how-can-i-troubleshoot-jira-portfolios-scheduling

I couldn't find it because I apparently posted that from another account for some reason.

From that thread, here is my example: https://cl.ly/1U3C3k093s44

I was trying to schedule that OMNIA-6 task to start next.  It absolutely refused to do that.  After spending way too much time hassling with it, I gave up and planned out the sprints manually.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase

The benefits of using Jira in different departments

Jira is a great tool to use across different departments. Forget that paperwork – switch to Jira and get that tasks done smoothly. Marketing Jira allows for a complete digital transformation of you...

143 views 0 8
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you