Why is the Schedule by Person view not reflecting assignments?

I have a Plan set up for a team, all team members have been added and I've put a few assignments to individuals. When I look at the Plan grouped by person, the assignments are not reflected at all and issues are shown under other team members. How do I get this view to reflect actual workloads? Below, all "MyCardRules" issues are assigned to Maria and all "Zelle send money" issues to Nathan. The other team members should have no assignments. 

Screen Shot 2019-07-25 at 1.47.50 PM.png

1 answer

1 accepted

0 votes
Answer accepted

I've figured this out. A combination of correct Import settings and using the Calculate button.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,425 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you