Why does shared teams not cut across two plans for capacity

I have shared teams across two plans.  The plans are not showing over allocation in capacity when using the same teams in the two plans.

  • Shared Team 1 has 400 hours of capacity per sprint.
  • Plan 1 has sprint 1 allocating 400 hours to this shared team
  • Plan 2 has sprint 1 allocating 400 hours to this shared team

There is not any call out of over capacity between the two plans even though technical the team is now working 800 hours when you combine the two  plans for sprint 1

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,713 views 23 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you