Why are sprint dates overwritten when auto scheduler is run?

I am just learning portfolio and don't understand why the auto scheduler is overwriting my sprint dates when auto scheduler is run.  How to I ensure work already assigned to a sprint is preserved when the auto scheduler is run?

1 answer

Hi, Julia

Thanks for your question.

According to the document https://confluence.atlassian.com/jiraportfolioserver/auto-scheduling-issues-967895245.html , Auto-scheduler will not override the assigned sprint if you config the auto-scheduler only to override the empty value.  So you should make sure that you have configured it correctly.

If in your plan, sprints are still changed by the auto-scheduler, could you provide more details about how to reproduce the question?

Thanks!

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,749 views 24 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you