Why, after accepting an auto-schedule, do team capacities not change?

Jira Portfolio 3.0, new experience.

 

My team are starting to use Jira Portfolio 3.0.  When we run an auto-schedule, the plan shows some teams are over capacity in certain future sprints. OK.  But if we accept the suggested changes, then the same team capacity changes do not seem to persist in the plan.

This is what we see before accepting an auto-schedule:

before_accept.PNG

and this  what we see after:

 

after_accept.PNG

 

Are we missing something?

1 answer

0 votes
Ana Retamal Atlassian Team May 24, 2019

Hi Andrew,

we'll need more information to help you find the root cause of this issue, so I've created a Support ticket for you, you should have received a notification in your inbox. The Portfolio team will contact you and continue assisting you.

If you need anything else in the meantime, let us know!

Best regards,

Ana

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,638 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you