What is the correct filter for Portfolio

Deleted user Sep 19, 2018

I am having an issue where portfolio is trying the schedule tasks that are already done.

I have 3 teams my sources are a board for each team and an overall board

 

The team boards have a filter

"Project = CT and Team = 1"

"Project = CT and Team = 2"

"Project = CT and Team = 3"

and the overall board is 

"Project = CT"

 

Portfolio is trying to schedule Done issues in the future.

I need the Done issue on the team boards otherwise when an issue is moved to Done it will be removed from the scrum board.

Also can Portfolio calculate past velocity if you don't bring in the Done issues.

 

Thanks

 

1 answer

0 votes

Hi @[deleted]

In case those Done issues don't have a *resolution* select, Portfolio will not consider them as completed issues and will try to schedule them until you provide a resolution for them.

Could you please double check if this is the problem here? :)

 

Gabi

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira

⏰ Day in the life of a Jira Admin!

Hello Community! We thoroughly enjoyed this just-for-fun conversation in the Jira Admin Group about what it's like to be a Jira Admin. For #JiraJuly, our talented designers created these graphics t...

100 views 1 7
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you