You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi
We are currently trialing Portfolio, one odd thing I've noticed is that even though my issue sources are set to the correct projects for my teams, they dont seem to be automatically filling the teams field. Some are, some arent, majority arent.
The Add & Pay project key is DPP
Hi @Stephen Letch,
There's a few reasons why an issue won't be assigned to a team.
First of all, issues need estimates in ordered to be scheduled, which should assign them to a team. Make sure you assign estimates to your issues.
Your team members also need to have the correct availability and capacity in order for the team to be assigned. You can see more information on that in the docs here. You might want to look at the capacity per team member to see which members are available or not. See the docs here for more information on how to do that.
Cheers,
Clare and the Portfolio team