You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
What is the value of Target dates in Advanced Roadmaps? I can add them in the fields view but they do not auto chart a timeline on the data area but Start and End Date due? So why would I use the Target Start and end? Just
Hi @Channing Childs ,
Under the Configure > Scheduling section - you can change which fields affect your timeline - so, if you like to set Target Start and Target End that would work.
Please note that if you make this change in the settings, the Auto-schedule will now update your Target Start/End fields.
Having said that, the way I use them (since Portfolio for Jira) is to keep a static value of my "original" plan - the values I enter manually; and leave the Start Date and Due Date to be updated by the Auto-schedule based on the available data (team capacity, velocity, priority, estimates...etc.).
Hope that helps.