Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,551,971
Community Members
 
Community Events
184
Community Groups

Stories in backlog are being scheduled by Portfolio

I want Portfolio to show dependencies between stories so that Portfolio can schedule a story that is blocked by few other stories after all the stories that are blocking a particular story are closed.But Portfolio is not showing dependencies at story level like it shows the same at Epic level with a different color header and footer for the dependent Epic.

Also Portfolio is scheduling all the items in backlog in random sprints all by itself , I want to have the over ride to schedule my backlog items in future sprints by my self and not by Portfolio ...

Has any one ever encountered this situation ??

1 answer

Yes, I have the same problem with Portfolio 'self-scheduling' into sprints. It is super annoying and I have no solution for you. I just wanted to let you know that you are not alone. 

I have two issues here , 1 Portfolio auto scheduling backlog items from board into random sprints and 2 the stories that are blocked by some other stories are being scheduled in portfolio before the completion of story that the current story is dependent on . I understand you have self-scheduling issue but what about the other one 

??