Progress bar clears when issues are moved to done.

David Wilson October 11, 2018

I have recently started playing with Portfolio for jira and am running into some problems with the progress bar.  Here are a few details to give some context.

When setting up my plan, I am only filtering for the project (Project = XYZ).  No other board filters or status filters are being applied so I should get everything.

On my Portfolio plan, I am filtering for all issues, all statuses, and with a time from of the entire 2018 calendar year.

So when I move an issue to Done on my scrum board, I will go to my Portfolio plan and refresh the page.  When I do that, the progress bar updates and shows green, indicating progress to the parent and the release.  When I hit the "Calculate" button, the closed issue goes away and my progress bar shows no progress.

Is this supposed to happen?  And is there a way I can get the Done items to show so the progress bar can show actual progress?

1 answer

0 votes
Moga
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 17, 2018

Hi David,

For some version of Portfolio, you will need to add the Completion date filter for show completed issues.