Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,369,738
Community Members
 
Community Events
168
Community Groups

Portfolio scenarios - changing sprint duration

Edited

I currently have the default sprint duration in Portfolio set to two weeks.  I want to create a scenario where the sprint duration is three weeks instead of two (for all sprints, not just one).   Can I do that without changing the configuration for all scenarios in the plan?

 

To clarify, I see other questions where users want to have a custom sprint duration to accommodate holidays and what-not.   In other words, they run 2 weeks sprints, but a few times a year want to make it a 1 week or 3 week for the holidays.    I am not asking this question.

1 answer

0 votes
Thomas Atlassian Team Aug 13, 2017

Hi @Vanessa_Roberts,

 

If you change the sprint duration of a team it will then become part of the scenario as an uncommitted change, as long as this is not committed it won't impact other scenarios. You are not able to change the duration of an active started JIRA sprint.

Note: while from my personal experience I would generally advise to keep the number of uncommitted change to a minimum to ensure it doesn't grow out of control, it seems OK for your use case.

 

Cheers,

Thomas

Suggest an answer

Log in or Sign up to answer
TAGS

Atlassian Community Events