Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,558,367
Community Members
 
Community Events
184
Community Groups

Portfolio not respecting backlog ranking or priority

Edited

I have a project in Jira and Portfolio that is using a two-week sprint (current sprint is in progress and showing up correctly), with a stack-ranked backlog in Jira, and story priorities set as blocker or major. No epics are included.

Portfolio is currently filling upcoming sprints for a release with stories in the wrong order. That is, the backlog stack ranking is not maintained. 

I have looked through all the explanations of ranking and sorting and I cannot find a reason that portfolio would do this.  Can anyone offer an explanation?

 

eta:

Jira Cloud 958ff764

Portfolio for JIRA - 1000.105.0

 

1 answer

Hi Shay. 

So, same problem here.. 

As I understood, the logic is something like this:
- portfolio reads the stories at the right order 

- it will allocate the story1 to the week or sprint IF there is available "space" for it

- if there is not enough space for the story1, it'll get the next story(2) and try to allocate at the available space.. and so forth... that's the reason sometimes (or always) you don't have your planning at the order you've specified. 

- and worst.. it understands that epics (without stories) can be fitted anywhere.. at least for this problem we found a solution: create one story at this epic and use estimates here.

I don't agree with this behavior because it's not realistic. I won't start story 50 just because it fits at this week..  It's causing us a lot of problems here.. 

That behavior is as designed, as confirmed to me by Atlassian.

I strongly disagree with this approach and have had to stop using Portfolio because of it. Backlog ranking is incredibly important and you should have control of it.