Hi,

 

In portfolio, I have team members with let's say 8Hrs capacity per day.

I assign 2 user stories to team member X.

Story 1: 16Hrs. Start date: 01/07/2017
Story 2: 24Hrs. Start date: 01/07/2017

Doing like that I will have the stories one after another according to backlog priorities.

But what I would like to do is to have my team member work 4 hours per day on project A and 4 hours per day on project B so both user stories run in parallel for the same team member.

Another example would be to assign a routine task to a team member, let's say 1 hour per day, and he would work on other stories the remaining 7 hours.

 

How can this be done in portfolio ?

 

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,528 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you