When I started using Portfolio, the Later release didn't contain any start or end date. But recently I noticed that in some cases (plans) a start and end date is actually assigned to the Later release...and the start date is not always after the end date of the last known release in the plan.

What is the reason for this? Can we change it? 

Thanks in advance

Later release.jpg

1 answer

0 votes

Hi Christophe,

Later release is the placeholder for all the issues that scheduler cannot schedule into any of the releases. The Later release is used as a last resort by the scheduler.

The start date of the Later release is the start date of the issue starting first. User cannot change this date as issues cannot be assigned manually to Later release.

I hope this helps.

Regards,

Portfolio for Jira.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,647 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you