Portfolio Plan not synching after updating a Task in JIRA (3.13.0)

Edited

We are using version 3.13.0 of Portfolio Add On with JIRA v8.2.4.  

When I update a Task with an Epic in Jira the  change is not reflected in my plan within Portfolio. 

Below are the options that I see.

 

Capture.PNG

1 answer

0 votes
Kathy Hart Community Leader Nov 05, 2019

In my experience, you have to click on Calculate or the calculator icon (depending on your view) on the Portfolio Plan page to get tickets updated in Jira to reflect the changes in Portfolio. 

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Confluence

Wouldn't it be nice to have this Jira-Confluence integration?

...ossibility became true in a not too far future, project/space access would be left in the hands of all team members. Don't get me wrong: I'd love it! However, it would also be nice to have a way in which j...

60 views 0 1
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you