You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hello,
In Jira Advanced Roadmap, is it possible to create a plan that we defined in a big planning session and an actual plan of what the actual execution of the plan looks like right now.
We would like to put the planning and the actual side by side all the time. The goal is to see how big our deviations from the "planned" plan are.
Is that possible to create something like that in Jira Advanced Roadmaps?
Thanks for any help!
Theresia
Hi Theresia,
You can use Scenario's for that!
Scenarios let you experiment with how work is scheduled across different versions of your plan. With multiple scenarios in place, it's easier to assess the impact of unplanned risks on the ability of your teams to deliver work on time.
Have a look at this resource:
https://confluence.atlassian.com/jiraportfolioserver/using-scenarios-965567135.html
Jeroen
Hi Jeroen,
amazing thank you for your help that is exactly what i'm searching for. :)
Best,
Theresia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Theresia!,
If this answer was helpful, please accept so other users can find the answer too :-).
Jeroen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.