amine benali April 15, 2019

Hello Team,

1- go to Team's Capacity in your Portfolio Plan

2- Use Exceptions in the Team's capacity section in order to simulate changes of capacity during some periods

 

Result after Calculate => Exceptions are not taken into consideration !! 

2 answers

1 vote
Areli Ibarra
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 19, 2019

I"m actually having the same issue. I was running the schedule report and I was not seeing any purple on my sprint when people is out.

Double check people Exceptions thinking maybe I did nt entered the hours for the exceptions, but they are there.

I hope is just a graphic issue and not an algorithm, as is very critical for me to understand if we are over allocating work.

0 votes
amine benali April 19, 2019

Hello @Areli Ibarra 

 

If you notice even the target dates are not displayed....

After several hours of analysis, the problem comes from the activation of the new experience of planning....(the value in the data base shows the new experience while the dispay is the old one experience)

1- You need to ACTIVATE the new experience.

2- WAIT until you SEE YOUR FULL PLAN DISPLAYED.... NO NEED TO HIT CALCULATE 

3- DISABLE the new experience...wait untill your plan is displayed fully.

4- Then hit CALCULATE 

Keep me informed if this works for you :)