When assigning someone 10 days for a task, the plan in portfolio counts the weekend as working days, so if they start on the 1st they will finish on the 10th. Is there any way to remove weekends from the picture so that it will only count the working days and inside go from the 1st to the 12th?
Hi Katerina,
Welcome to the community. You can configure the working days by:
The documentation is here: https://confluence.atlassian.com/jiraportfoliocloud/configuring-working-hours-and-days-828785191.html
It's also worth looking at the working days configured for your individual boards so the teams can see what's happening too. Read more here https://support.atlassian.com/jira-software-cloud/docs/configure-working-days/
Hi!
I have a same problem. But I didn't find that kind of option under the configure to change working days. And board calendar setting were not affected to plan schedule
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.