Is it possible to create a plan over multiple teams using target date instead of calculated end date

Daniel Brenner
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 15, 2021

While trying to aggregate multiple plans from differnt teams into one programm plan Jira uses a calculated end date and not the target date from the individual plans for each epic. some Initiatives/Epics out of the hierarchy aren't even shown in the aggregated plan. is there a fix to use only the target date for such a plan?

1 answer

0 votes
elizabeth_jones
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 15, 2021

Yes, if you have target start and end, as I do. In the configuration screen you can choose those. Screen Shot 2021-04-15 at 4.52.56 PM.png

 

As an example, I have created a project to house all initiatives. I have a plan that pulls in all initiatives from that project and then displays them on the roadmap by target start and target end dates. Hope this helps :)