Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,560,577
Community Members
 
Community Events
185
Community Groups

In Portfolio When making changes to my team hours and adding resources schedule does not change

Edited

I am making changes to my team and weekly hours in JIRA Portfolio and my schedule does not change. What am I missing!? 

  • Scrum project/2 week iterations
  • Using hours (not story points)
  • I have 7 team members assigned to my project
  • Only 5 team members take on actual work - at 35 hours a week

**Using the latest portfolio version

Questions

  1. On the Team Page: When assigning my team weekly hours - do I only add 35 hours for one week and it calculates that we are doing two week sprints? Or should I add 70 hours to account for two weeks?
  2. I tried to add more hours to my team work load, I added virtual team members, and it seems to not change my schedule at all. Could this be because of dependencies, we do have some?
  3. I also went into each individual team member under their name and added any exceptions, if they would be on Holiday or Having PTO, does the schedule take that into consideration? 

1 answer

Hi Natalie,

 Dunno if you've found the answer elsewhere yet.

Your questions as I understand it:

  1. Its weekly hours so reference that
  2. I think this is more likely to be linked to your iteration length and velocity settings for the team
  3. Yes the schedule should factor in exceptions that you add

You may also want to check your plan settings for the following:

  • Planning unit
  • Sprint length*
  • Default velocity*
  • Working hours and days

*I think the teams settings on these will override the plans. Although i'm unsure.

Since you haven't mentioned the sprint cadence portfolio will just think you have a less efficient team delivering the same amount of story points. I generally work on an 80% efficiency model so in theory if you went simplistically as 1 story point = 1 day. Each team member you add should = 8 points of cadence and that way your schedule should scale accordingly.

 

Hopefully helps!

Thanks

Lewis