Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

In Portfolio When making changes to my team hours and adding resources schedule does not change

Edited

I am making changes to my team and weekly hours in JIRA Portfolio and my schedule does not change. What am I missing!? 

  • Scrum project/2 week iterations
  • Using hours (not story points)
  • I have 7 team members assigned to my project
  • Only 5 team members take on actual work - at 35 hours a week

**Using the latest portfolio version

Questions

  1. On the Team Page: When assigning my team weekly hours - do I only add 35 hours for one week and it calculates that we are doing two week sprints? Or should I add 70 hours to account for two weeks?
  2. I tried to add more hours to my team work load, I added virtual team members, and it seems to not change my schedule at all. Could this be because of dependencies, we do have some?
  3. I also went into each individual team member under their name and added any exceptions, if they would be on Holiday or Having PTO, does the schedule take that into consideration? 

1 answer

Hi Natalie,

 Dunno if you've found the answer elsewhere yet.

Your questions as I understand it:

  1. Its weekly hours so reference that
  2. I think this is more likely to be linked to your iteration length and velocity settings for the team
  3. Yes the schedule should factor in exceptions that you add

You may also want to check your plan settings for the following:

  • Planning unit
  • Sprint length*
  • Default velocity*
  • Working hours and days

*I think the teams settings on these will override the plans. Although i'm unsure.

Since you haven't mentioned the sprint cadence portfolio will just think you have a less efficient team delivering the same amount of story points. I generally work on an 80% efficiency model so in theory if you went simplistically as 1 story point = 1 day. Each team member you add should = 8 points of cadence and that way your schedule should scale accordingly.

 

Hopefully helps!

Thanks

Lewis

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Apps & Integrations

Send an Email or Publish to Confluence - What should you do with your release notes?

Background When you hear the words ‘Release notes’, almost always you think of an unsolicited email from a software vendor. But I am here to tell you that from our data, sending release notes via E...

130 views 1 2
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you