In Jira Portfolio 3.x is there a way for parent issues to inherit target start/end dates?

In Jira Portfolio 3.x is there a way for parent issues to inherit target start/end dates or custom dates? I want the parent issues to take the earliest start & latest end dates and display that as their start/end.

 

Doesn't have to be Target, could be a custom field.

1 answer

1 accepted

0 votes
Answer accepted
Raathi Atlassian Team Jul 26, 2019

Hi Sophie,

Right now Portfolio 3.0 doesn't rollup dates to the parent issues. But we are working on a solution for this.

Regards,

Raathi

Hi, any update on what you are working on please?

Raathi Atlassian Team Mar 25, 2020

The rollup dates functionality is now available in Portfolio. You can read about it here in detail.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,645 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you