In Jira Portfolio 3.x is there a way for parent issues to inherit target start/end dates or custom dates? I want the parent issues to take the earliest start & latest end dates and display that as their start/end.
Doesn't have to be Target, could be a custom field.
Hi Sophie,
Right now Portfolio 3.0 doesn't rollup dates to the parent issues. But we are working on a solution for this.
Regards,
Raathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.