Hi,
I have built my company roadmap into portfolio.
It is quite complex with several initiatives and epics. I have manually allocated teams to the various epics (for simplicity we defined only one stage - implementation, and one skill - development).
I have also defined a few versions with dynamic end dates, allocating each epic to a version.
Some dependencies are defined but a lot of the epics are not dependent on anything.
The problem I see is that at least one of the teams has gaps / empty sprints in the middle of their workplan, while the epics that populate the plan after the gaps could have started earlier (no dependencies). These epics belong to release 3 (meaning there are two releases beforehand) but I do expect the team to start working on them as soon as they are available, even if other teams are still working on release 1 or 2.
Even if I set the release 3 (and release 2) start date manually to today, this problem persists.
How can I resolve this?
Thanks
Ran
Solved! Go to Solution.
Community moderators have prevented the ability to post new comments.
Thanks, this indeed resolve the issue. Sorry for the late reply.
Ran
Hi, I seem to be having the same problem. My plan is using only 36% of the team capacity and it is full of Gaps (empty sprints). The plan rolls out to 2018!
Can you help?
Thank you!
Community moderators have prevented the ability to post new comments.