Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

How to resolve under-utilized / empty sprints in portfolio automatic planning

Ran Zaksh January 5, 2015

Hi,

I have built my company roadmap into portfolio.

It is quite complex with several initiatives and epics. I have manually allocated teams to the various epics (for simplicity we defined only one stage - implementation, and one skill - development).

I have also defined a few versions with dynamic end dates, allocating each epic to a version.

Some dependencies are defined but a lot of the epics are not dependent on anything.

The problem I see is that at least one of the teams has gaps / empty sprints in the middle of their workplan, while the epics that populate the plan after the gaps could have started earlier (no dependencies). These epics belong to release 3 (meaning there are two releases beforehand) but I do expect the team to start working on them as soon as they are available, even if other teams are still working on release 1 or 2.

Even if I set the release 3 (and release 2) start date manually to today, this problem persists.

How can I resolve this?

Thanks

Ran

3 answers

1 accepted

0 votes
Answer accepted
Martin Suntinger
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 5, 2015

Hi Ran, I've investigated this, and based on your description it is certainly expected that the epic in release 3 is scheduled as soon as a team is free to do it, given the release date is set as a fixed date allowing for an overlap between the releases. 

It seems this was a scheduling bug related to dynamic release dates (the behaviour is not reproducable with fixed end dates). 

We've released 1.8.2 just now containing a fix for this - could you verify if this resolves the issue? Big thanks for uncovering this! 

Martin Suntinger, Product Manager for JIRA Portfolio

 

0 votes
Fernando Taliberti January 21, 2016

Hi, I seem to be having the same problem. My plan is using only 36% of the team capacity and it is full of Gaps (empty sprints). The plan rolls out to 2018!

 

Can you help?

 

Thank you!

0 votes
Ran Zaksh January 25, 2015

Thanks, this indeed resolve the issue. Sorry for the late reply.

Ran

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events