Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,560,113
Community Members
 
Community Events
185
Community Groups

How to adjust timeline base on dependencies?

I have 2 tasks with a Finish to Start dependencies. How to I get the start date of Task B to be automatically pushed out when Task A end date is pushed out? 

 

2022-06-07_7-17-10.png

2 answers

1 accepted

0 votes
Answer accepted

@Michael Andolfatto 

I've been looking for an answer to the same question for a while now :D 

I've never used the auto-scheduler before, this doesn't work with manually adjusting start/finish of a task by any chance, does it?

Michael Andolfatto
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Jun 08, 2022

Hey @Anna Poppe ,

No, there is no functionality for this as far as I'm aware. The blocked task will only have its position adjusted by the auto-scheduler or manually by a user moving it directly.

I would definitely recommend playing around with the auto-scheduler- it can be really helpful to use it as a foundation of sorts for your plan's timeline which can then be adjusted manually afterwards.

Like # people like this
1 vote
Michael Andolfatto
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Jun 07, 2022

Hi @Jean-Francois Thibault ,

You'll need to make sure your plan is configured for sequential dependencies rather than concurrent. This can be verified in the Plan Settings > Scheduling.

If sequential dependencies are enabled, Advanced Roadmaps will automatically schedule Task B after Task A. (as long as the global settings for dependencies are configured this way- you need to be an administrator to verify this)

If Tasks A and B have inherited Sprint dates and are scheduled accordingly, you will need to make sure that the auto-scheduler is set to overwrite Sprints rather than filling in empty values.

@Michael AndolfattoI've checked our settings.  All set to sequential. Currently we are planning on Initative level only (without epics/stories/sprints). Initative A+B+C all linked with a "blocks" dependency. Initially all of them were auto-planned. All fine. Then I've moved Initiative A to a later start date, overlapping Initative B. Automated Planning of B+C (without A) won't change anything. B ist overlapping A. Appreciate any help, hint, comment. Regards and thanks in advance.

Michael Andolfatto
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Jan 30, 2023

Hi @Raimund Antonitsch , the auto-scheduler in Advanced Roadmaps will only move issues that have estimates applied (either time or story points) which is very rarely the case for high-level issues like Initiatives.

Advanced Roadmaps really excels from the bottom-up: the start date/end date of an issue like an Initiative is dependent on the scheduling of the lowest-level (estimated) items.