Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,552,123
Community Members
 
Community Events
184
Community Groups

How to Implement a 1 Team Member Works on 1 User Story Policy in Portfolio?

Hi,

I am doing my first test plan (improved interface):

  • I have 3 epics x 2 issues each, all with 2d estimation.
  • I have a team with 2 members each with 40 hours per week capacity equaling 5 days per week.

Portfolio squeezes all issues to just one day implementation, implicating (I guess) that both team members work together on all issues and thus are able to finish them off in just one day.

Is there any configuration magic to avoid this? Especially in software development it is completely unrealistic to put two developers on the same task.

 

Thanks and regards,

Anton

1 answer

0 votes
Thomas Deiler
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Jul 18, 2019

Dear @Anton Maleev 

Especially in software development it is completely unrealistic to put two developers on the same task.

This is not the whole truth: https://en.wikipedia.org/wiki/Pair_programming

So long

Thomas

Thanks @Thomas Deiler ,

good point, I take the "completely unrealistic" back :)

Follow up:

https://confluence.atlassian.com/jiraportfolioserver/auto-scheduling-issues-967895245.html

(quote - table transposed)

Technical details: Maximum people assigned per story
Live plans (versions 2.0 to 2.27): You can configure how many people can be assigned to a story.
Plans with the improved interface: Only one (1) person can be assigned to a story.

Puzzling, because I was working with an "improved" plan. Anyway, I switched several times between "live" and "improved" and it suddenly started working as I expected. Worrying that I didn't understand why, though.

Suggestion to Atlassian:
Could be a good idea to expose as much as possible of the governing parameters as configuration options. It would even help to see read-only stuff, just in order to know, how the engine takes its decisions.

Best regards,
Anton

Second Follow-up:

I just found out that the configuration for "live" plans is much more verbose than that of the "improved" plans.

It appears to me the "improved" plans are still "work in progress". I am also missing completely the "capacity" information on the plan there.

We will stick to the "live" plans until the "improved" ones are ... improved :)

We are running 3.6.1 and will keep updating.