How do you deal with issues that take more time than manpower-time?

My question is how to include issues into roadmap planing that take 10 days, but only require 5 days of real work because there is some external dependency. As a consequence the engineer only needs to be blocked by 5 days, but the whole issue needs to be planned with 10 days. Any suggestions?

1 answer

Have you considered using sub-tasks within the issue.

  • Sub-task one for 5 days as external work.
  • Sub-task two for the engineer, but blocked by sub-task one.

@Steve Thornhill _Adaptavist_ Thanks! And then assigning the external sub-task to a fictive "external" team?

Yep, the sub-task doesn't need to be assigned, but if you are likely to use it for reporting then it would make sense to have an 'external' user/team rather than just being unassigned.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,649 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you