Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,559,696
Community Members
 
Community Events
185
Community Groups

How do you deal with issues that take more time than manpower-time?

My question is how to include issues into roadmap planing that take 10 days, but only require 5 days of real work because there is some external dependency. As a consequence the engineer only needs to be blocked by 5 days, but the whole issue needs to be planned with 10 days. Any suggestions?

1 answer

0 votes
Steve Thornhill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Feb 21, 2018

Have you considered using sub-tasks within the issue.

  • Sub-task one for 5 days as external work.
  • Sub-task two for the engineer, but blocked by sub-task one.

@Steve Thornhill Thanks! And then assigning the external sub-task to a fictive "external" team?

Steve Thornhill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Feb 21, 2018

Yep, the sub-task doesn't need to be assigned, but if you are likely to use it for reporting then it would make sense to have an 'external' user/team rather than just being unassigned.