How do you deal with issues that take more time than manpower-time?

My question is how to include issues into roadmap planing that take 10 days, but only require 5 days of real work because there is some external dependency. As a consequence the engineer only needs to be blocked by 5 days, but the whole issue needs to be planned with 10 days. Any suggestions?

1 answer

Have you considered using sub-tasks within the issue.

  • Sub-task one for 5 days as external work.
  • Sub-task two for the engineer, but blocked by sub-task one.

@Steve Thornhill Thanks! And then assigning the external sub-task to a fictive "external" team?

Yep, the sub-task doesn't need to be assigned, but if you are likely to use it for reporting then it would make sense to have an 'external' user/team rather than just being unassigned.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Confluence

An update on Confluence Cloud customer feedback – June 2022

Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...

171 views 1 3
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you