Hi
I have a few issues, 4 Done, on my board, which are the issue source for my plan, that are in status- done- are showing up on my board (attachment 1) but are not showing up on my plan (Attchment2)?
I tried moving them, on my board, from Done column to another column- this didn't fix the problem.
Any Help
Hi @Guy Shimoni ,
On the plan configuration, go to "issue sources" tab and you'll find a field "Completed issues" where you can choose how long any completed issues in Jira will remain in your plan.
change to 100 / 364 / 1000 , and you'll see your issues.
Thanks,
Elad.
I set up the "Include completed issues" parameter for 1000 days, but completed issues are missing in the plan. We are using Jira Server.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.